Replacement of the Bridge at pk78+650 of the Ressano Garcia Line

  • Location: Guaza, Mozambique
  • Solution: Bridges
  • Type: Railway bridges
  • Promoter: CFM – Mozambique’s Ports and railways Authority
  • Client: CFM – Mozambique’s Ports and railways Authority
  • Scope: Structural Design, Inspection, Geotechnical, Drainage, Flood Protection and Hydrological Studies
  • Project: 2013
  • Construction: 2014
  • Contractor: Tecnasol
  • Dimension: 25m long
  • See on Google Maps

Replacement of the Bridge at pk78+650 of the Ressano Garcia Line

  • Location: Guaza, Mozambique
  • Solution: Bridges
  • Type: Railway bridges
  • Promoter: CFM – Mozambique’s Ports and railways Authority
  • Client: CFM – Mozambique’s Ports and railways Authority
  • Scope: Structural Design, Inspection, Geotechnical, Drainage, Flood Protection and Hydrological Studies
  • Project: 2013
  • Construction: 2014
  • Contractor: Tecnasol
  • Dimension: 25m long
  • Ver no Google Maps

The Ressano Garcia line provides communication between Mozambique and South Africa. It is a line used for heavy rail traffic, for transporting goods (ore and cereals) and passenger traffic. It allows the supply of services to "hinerland", exporters and with the need for fast transport and access to international traffic ports for the diffusion of products in foreign markets. This rail corridor controls the uninterrupted flow of goods from the Agro-Industrial catchment area south of Save and is therefore of essential importance.

The existing bridge was replaced by a simply supported steel deck, with a single span of 20.40m. The deck is composed of a grid system consisting of two 1.35m high web girders, transversal beams 3.40m apart, and two central stringers that receive the entire track system.

The deck is supported on reinforced concrete abutments, which were built in front of the abutments of the previous construction.

Other projects

Second bridge over the Matola River, pk26+900, on the Ressano Garcia Line

Second bridge over the Matola River, pk26+900, on the Ressano Garcia Line

See more
Replacement of the Bridge at pk50+200 of the Ressano Garcia Line

Replacement of the Bridge at pk50+200 of the Ressano Garcia Line

See more
Pedestrian Bridge over Sizandro River in Torres Vedras

Pedestrian Bridge over Sizandro River in Torres Vedras

See more
Bom Sucesso Walkway

Bom Sucesso Walkway

See more
KaTembe’s Urbanization Plan

KaTembe’s Urbanization Plan

See more
Nossa Senhora da Guia Bridge in Ponte de Lima

Nossa Senhora da Guia Bridge in Ponte de Lima

See more
Top

We use cookies to improve your browsing experience. By continuing to access this website you are agreeing to their use. For more information see our cookie policy.

Portugal 2020 / Compete 2020 / União Europeia - Fundo Europeu do Desenvolvimento Regional